Talk · May 7, 2026
Permitting Streamlining Update and Real World Bottlenecks
- Event
- Arkansas Environmental Federation, Air Seminar, Wyndham Riverfront, North Little Rock
- Role
- Co-presenter
- With
- Walter Wright (Mitchell Williams)
- Topic
- Permitting
See the full slides
About the talk
Waiting for an air permit can hold up a project for months. This session looked at the bottlenecks facilities meet in practice and at the tools Arkansas already has to shorten them, then at the work underway to speed permit review further. It was given with Walter Wright, whose part covered the broader efforts.
Key points
- DEQ’s quick guide. DEQ’s Permit Flexibility and Streamlining Conditions Quick Guide lists the tools available to speed permit issuance and renewal. For air permits at minor sources, and where no federal requirement is violated, it lists DEQ’s consideration of requests to extend a testing, compliance or other date (in writing at least 15 days ahead), for a temporary emissions exceedance or alternative testing or monitoring (at least 30 days ahead), and for alternative monitoring (at least 30 days ahead, folded into the next permit modification). Approved operating scenarios and streamlined conditions in the final permit can be used without further revision or notice.
- Alternative operating scenarios. Any operating scenario a permit allows can be used with no permit revision or notice to DEQ. The applicant asks for reasonably anticipated scenarios at the time of application, and DEQ includes the approved ones in the permit.
- Administrative amendments. These cover typographical errors, changes of name, address or phone number, more frequent monitoring or reporting, retiring equipment, and changes to the insignificant activities list. Under Parts 40 and 41 they take effect on approval; under Part 42, on submittal, with 60 days for DEQ to act.
- Changes with no emissions increase. The change cannot be a modification under Title I, exceed permitted emissions, violate applicable requirements or contravene federally enforceable monitoring, recordkeeping, reporting or certification terms. It takes seven days’ advance written notice to DEQ; Part 42 also requires notice to EPA.
- Case scenarios. Scenarios covered a vehicle assembly plant needing a permit modification; permit flexibility (deadline extension, temporary emissions, alternative monitoring, and the federal alternatives in the general provisions of 40 CFR Parts 60, 61 and 63); a de minimis or minor permit modification; a pharmaceutical plant adding a crystallizer, which needs a significant modification; and a vehicle plant adding a stamping and paint line.
- Extraordinary tools. Temporary variance, interim authority, and the emergency or upset affirmative defense. The quick guide says the director may grant a temporary variance or interim authority for compelling reasons and good cause once DEQ has an administratively complete application; interim authority does not apply to PSD, lasts up to 90 days, and is decided within ten days of the request.
- Expediting programs elsewhere. Walter Wright’s part of the session discussed AEF’s work to replicate programs in Texas, Oklahoma, Mississippi, Louisiana and Georgia that expedite permits using contractors or willing agency employees. AEF had discussed draft enabling legislation with DEQ that would let DEQ run such a program using either, across all of its permit programs, with rules to follow.
- Outdated permit terms. The AEF committee has searched for permit terms that may be unnecessary, duplicative or outdated, through committee discussion, talks with DEQ and a survey of members.
- Executive order. The session discussed the Governor’s Executive Order 26-04 of February 16, 2026, which requires cabinet-level agencies and boards that issue permits and similar approvals to review those processes within 120 days and to submit a written improvement plan within 180 days.
- The federal landscape. The deck closed with the state of federal action as of April 2026: EPA’s March 2025 reconsideration package, an April 16, 2026 EPA memo on Title V renewal streamlining, and Clean Air Act bills that had passed the House and were awaiting the Senate.
Primary sources
Every link was checked on October 31, 2026.
Arkansas
- Arkansas DEQ: Permit Flexibility and Streamlining Conditions Quick Guide
The guide the talk walked through: date extensions, temporary exceedances, alternative monitoring, interim authority and temporary variance. - Arkansas Governor: Executive Order 26-04 announcement (February 16, 2026)
Requires a review of permitting processes within 120 days of the order.
Coverage
This page describes a talk given on May 7, 2026. It is a summary for general information, not legal or engineering advice, and the views are my own, not those of any employer.